- S7.5.12
- Where necessary, the edges of the reinstatement must be trimmed over part or all of slab depth to comply with the following requirements:
- The edge regularity must comply with the requirements of S6.8.6.
- Any undercutting must comply with the requirements of S6.8.10.
- Where the adjacent road slab has cracked as a result of the excavation operation, the damaged area of the slab must be removed and included within the area to be reinstated.
- Where, after trimming, the excavation extends to within 300 mm of a slab edge, a joint, ironwork or another reinstatement, the relevant area of the slab must be removed and included within the area to be reinstated.
- All edges must be cleaned and wetted before placing concrete.