- S6.1.12
- The backfill and sub-base must be reinstated to a permanent standard at the first visit
- S6.1.13
- The interim base must be granular and the interim surfacing must be in accordance with the requirements of S6.1.9 to S6.1.11.
- S6.1.14
- On the second visit, all interim materials must be removed to the top of the sub-base, and a permanent base, binder course and surface course laid.