Method Statement

A10.2.37
The producer must provide a method statement for the HBM detailing best practice for placement, compaction, curing and protection of the reinstatement, including procedures for cold joints, inclement weather, plant breakdown and record keeping.
A10.2.38
The statement must include the intended mixture constituents and proportions, with supporting data from the mixture design results from A10.2.11 to A10.2.16 and/or historic records to justify the constituents and proportions including water content.
A10.2.39
The statement must include a sample record sheet for submitting the data required in A10.2.17.
A10.2.40
The undertaker must not change construction procedures without the agreement of the producer.